Challenging times on 'high-speed Silk Road'

By Cui Jia | China Daily | Updated: 2013-07-12 07:38

Workers on new 1,776-km rail link no strangers to tough conditions, reports Cui Jia in Urumqi.

It was just after midnight in Hami prefecture in the Xinjiang Uygur autonomous region and the construction workers on the Lanzhou-Urumqi high-speed railway had just started work.

Challenging times on 'high-speed Silk Road'

Work proceeds on the Lanzhou-Urumqi high-speed railway, the longest such rail link under construction in the world. [Photo / China Daily]

The men work at night to avoid the intense heat of the day that causes the water in the concrete mix to evaporate too quickly and could compromise the strength of the bridge being built, making it too fragile to meet stringent safety and engineering standards.

The stifling summer heat is just one of the challenges facing the 30,000 workers on the Xinjiang section of the project.

The 1,776-km-long railway, which on completion will link the capitals of Gansu province and Xinjiang, crosses the desolate and inhospitable Qinghai-Tibet Plateau, the arid sands of the Gobi Desert and a number of high-wind areas. These features make construction of the rail link a difficult and risky task.

The project, dubbed the "high-speed Silk Road", is the longest high-speed railway under construction in the world and the first in China to be built partly across a plateau.

After five years' work in Gansu, Xinjiang and Qinghai province, the line is scheduled to be operational by the end of 2014. The team in Xinjiang expects to finish laying the tracks by November.

Currently, only one railway carries passengers and cargo in and out of Xinjiang, the old Lanzhou-Urumqi railway, which connects Xinjiang with the rest of China and also provides a link to Central Asia and Europe.

The new line follows hot on the heels of the 11,179-km Chongqing-Xinjiang-Europe International Railway, which officially came into service in 2012. The C-X-E starts in Chongqing, crosses the Alataw Pass, on the border with Kazakhstan, via the old Lanzhou-Urumqi railway, and then progresses through Russia, Belarus and Poland before terminating at Duisburg, Germany. The journey takes an average of 16 days, roughly three weeks faster than the ocean route from China's eastern provinces.

Previous 1 2 3 4 Next

Most Viewed in 24 Hours
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
 
主站蜘蛛池模板: 芦山县| 赤峰市| 寿光市| 四子王旗| 宾阳县| 雷山县| 隆化县| 怀化市| 敦煌市| 依兰县| 平江县| 东乡族自治县| 若尔盖县| 广河县| 萨迦县| 中西区| 邓州市| 仪陇县| 剑阁县| 汶川县| 红安县| 陆川县| 富顺县| 大埔县| 阳春市| 长宁区| 正定县| 陇西县| 嘉鱼县| 拜泉县| 米泉市| 定日县| 禹州市| 盐城市| 河间市| 荔浦县| 句容市| 岚皋县| 唐河县| 邢台县| 雷州市|